General:
- Planning:
- Application submitted 03/07/2015
- permission received 12/11/2015
- Lease agreement: 25 years
- DNO: accepted offer of WPD
- Subsidy mechanism: Grace period, 1.2 ROC
- Timing: Q2 2016
Technical:
- DC-capacity: 4.892 MWp
- AC-capacity: 3.96 MVA
- Assumed yield: 967 kWh/kWp (PV Syst, Meteonorm)
- Grid:
- 11KV connection
- 2.7 km cable route
- No upgrade works
- Structures: tables of 2 rows in portrait
- Central inverters
- Modules: Tier-one brand, crystalline 260Wp